Programmed Maintenance

Programmed maintenance means that a scheduled shut down will need to be planned for all cooling equipment once every three months for approximately 4 hours and one every six months for 8 hours. This may vary depending on tower size and location. This schedule has been designed to comply with the requirements of AS3666 Part 2 Operation and Maintenance. Only suitably trained personnel are authorised to carry out these works. This schedule does not cover the application of chemicals into the system for microbial control. A specialist water treatment company should be engaged to carry this out.

Recommended maintenance schedule for Evaporative Cooling Equipment over a 12 month period.


SERVICE

EVERY

MONTH

EVERY 3

 MONTHS

EVERY 6

MONTHS

EVERY 12

MONTHS

General overall inspection of tower condition

  •  

 

 

 

Drain and clean sump

 

  •  

 

 

Clean sump strainer

  •  

 

 

 

Remove access door and visually inspect inside of casing section

 

  •  

 

 

Remove nozzles and clean all debris

 

  •  

 

 

Remove fill and water blast clean

 

 

  •  

 

Remove eliminators and water blast clean

 

 

  •  

 

Water blast clean the entire tower

 

 

  •  

 

Tighten all loose bolts

 

  •  

 

 

Check and adjust fan belts

  •  

 

 

 

Check motor for noises

  •  

 

 

 

Check bearings for noises

  •  

 

 

 

Grease bearings

  •  

 

 

 

Check unit for vibration

  •  

 

 

 

Check mechanical section for any movement

  •  

 

 

 

Check motor volts and current

 

 

  •  

 

Apply anti-seize to adjusting bolts on motor

 

  •  

 

 

Check tip clearance on fan and adjust if necessary

 

  •  

 

 

Check pump for leaks and noises

  •  

 

 

 

Check tower bleed rate and advise chemical company if any problems

  •  

 

 

 

Check sump water level and adjust if necessary. Check valve operation

  •  

 

 

 

Consult with site maintenance engineer if any problems

  •  

 

 

 

Remove spray branches and flush out headers

 

 

 

  •  

Remove and clean air intake louvers

  •